2022.03.31 EPL_Facility Assessment Report

53 6.0. SUMMARY/GENERAL Summary of deferred maintenance cost analysis. Conditions for which recommendations have been identified have been categorized based on priority level: 1. Critical Condition: Life safety elements, serious building envelope conditions, critical structural concerns, failing systems requiring high maintenance 2. Observed Conditions: Moderate building envelope conditions, recommended repairs, systems nearing the end of useful lifespan, energy consumption issues, long term system upgrades, minor repairs The Summary of the Opinions of Probable Costs per each Section’s Recommendations is as follows: Critical condition recommendations = $xxxxx Observed condition recommendations = $xxxxx Our Opinion of total costs, including Construction and Non-Construction costs is $xxxxxxx. Please see the Matrix on the following pages for a detailed breakdown of costs.